Residential Project – Bellharbour, Co. Clare

Background

  • The site in located in the Burren in Co. Clare.
  • 200m2 single storey dwelling and garage.
  • Traditional dormer roof with a large attic for future use.

The challenge

  • Make most efficient use of budget due to excessive ground works as the site was sloping.
  • Construct a highly insulated dwelling.
  • Increasing cavity width for more insulation.

Building Matters Solution

  • Provided a full planning service.
  • Provided a set of full working drawings prior to construction including specifications
  • Set out site and foundations
  • Supervised and visited the project at different milestones.
  • Assisted and advised on all technical issues.

Results Achieved

  • Dwelling completed in September
  • High efficiency oil condenser boiler for heating and domestic hot water.
  • Completed new wiring of house with room stats for controlled heating.
  • Final costs within budget
Building Matters

Residential Project – Co. Limerick

Background

  • The site is located just off the N20 cork/limerick road
  • Two storey dwelling with garage.
  • 150m2 floor area.
  • 140m2 first floor

The challenge

  • Construct an A-rated dwelling
  • Use of HRV (heat recovery)
  • Instillation of Air to Water heat pump for heating and domestic hot water
  • Full fill cavity insulation and insulated slab on all external walls.
  • Use of air tight membranes for air tightness.
  • Make efficient use of budget .

Results so far

  • The time program is on schedule
  • Roofing completed
  • Windows installed

Residential Project – Co. Clare

Background

  • The site is located in North Clare.
  • Traditional 2 storey dormer construction.
  • 320m2 combined floor area.
  • 120m Garage to side.

Client’s Challenge

  • Create an A-rated Passive dwelling.
  • Timber frame construction.
  • Use of top end insulation.
  • Creating airtightness.
  • Install HRV. (Heat recovery ventilation)
  • Install a sustainable and energy efficient heat and hot water boiler.
  • Integrated vacuum system.
  • Integrated audio system.

Results Achieved

  • 11 month completion.
  • Completed new rewire of house with room stats for controlled heating.
  • Installed new gas combi-boiler for heating and instant hot water.
  • Final costs within budget.